health check
The purpose of Health Check is to provide the user a quick assessment of schedule soundness and credibility. Schedule integrity is determined by monitoring key indicators within a schedule that reflect both good and poor characteristics of schedule structure. These indicators are based on standard metrics and should be applied consistently to each schedule. The on-screen report generated provides the user with an understanding of the criteria ranges that are associated with e

trace path
The purpose of Trace Path is to see what is driving the start date or finish date of a task, allowing you to see how the selected task fits into the overall schedule. Running a trace on non-critical tasks can be just as important as the critical path. Driving and non-driving paths can be trace on a single project or multiple projects if inserted into a master project. Set trace driving on (single path) or off (multiple paths) Set path to trace predecessor and/or successors Se